EXMOUTH HOSPITAL
This project saw the complete refurbishment of the Hospital Kitchen for Exmouth Hospital. The existing kitchen did not comply with current standards, it was therefore completely gutted and received complete new plumbing, electrics, and fixtures & fittings. A modern high efficiency Kitchen Ventilation system was installed which improved working conditions and removed cooking odours.
Our Role
EDP carried out the full MEP Design and Specification for the new kitchen and supervised the implementation of the project. Because of the increased electrical load we also needed to assess the existing distribution system and design a suitable upgrade.
The Team
- Client
Devon Partnership Trust - Architect
Hart Ireson - Main Contractor
Dodd Group - Services Contractor
Dodd Group - Project Value
£ 300K
Systems Included
- Electrical Distribution
- Gas Supply
- Water Supplies
- Heating System
- Lighting
- Power
- Telephones
- Fire Alarm