NUFFIELD HEALTH STERILE SERVICES

The Sterile Services Decontamination Project involved creating 6 strategically situated Decontamination  Centre’s each servicing the operating theatre instrument sterilisation requirements for a cluster of up to 9 hospitals. Each unit was created in an existing 1100m2 industrial unit which was designed and “fitted-out” to healthcare and clinical laboratory standards to conform with the Department of Health’s new guidelines for Decontamination Centres (HBN 13).

Our Role

EDP Environmental was chosen by Nuffield Health to carry-out the detailed MEP and Process Design. Because the footprint of each site was different it was necessary to adapt the base design to suit each unit. During the process we worked very closely with two of the authors of Health Building Note 13 (HBN 13).

The Team
  • Client
    Nuffield Health
  • Architect
    Architect Design Group
  • Main Contractor
    CFES Limited
  • Services Contractor
    CFES Limited
  • Project Value:
    £25M
Systems Included
  • Reverse Osmosis Water Treatment
  • Clean Steam Generation
  • Standby Diesel Generator Set
  • UPS Systems
  • Integrated Control Systems
  • Steam Boilers with Dual Fuel System
  • Lamellar Flow Ventilation with HEPA Filters