SPIRE HOSPITAL – DUNEDIN

EDP Environmental were appointed by St Georges NHS Trust to prepare the RIBA Stage 4 design for the refurbishment of 4 number operating theatres within the hospital. The contractor was let as a Design and Build contract, and EDP Environmental were appointed as Contract Administrators and technical advisors on behalf of the Trust.

Our Role

The works were undertaken in a live environment, with surgical operations being undertaken in adjoining rooms, meaning noise and dust had to be kept to a minimum.

The Team
  • Client
    Spire Health Care
  • Architect
    CFES Limited
  • Main Contractor
    CFES Limited
  • Services Contractor
    CFES Limited
  • Project Value
    £ 3.5M
Systems Included
  • Electrical Distribution
  • Lighting & Power
  • UPS Systems
  • Ventilation
  • Heating & Water Services
  • Medical Gases
  • Access Control & Communications

project

NUFFIELD HEALTH STERILE SERVICES

The Sterile Services Decontamination Project involved creating 6 strategically situated Decontamination  Centre’s each servicing the operating theatre instrument sterilisation requirements for a cluster of up to 9 hospitals. Each unit was created in an existing 1100m2 industrial unit which was designed and “fitted-out” to healthcare and clinical laboratory standards to conform with the Department of Health’s new guidelines for Decontamination Centres (HBN 13).

Our Role

EDP Environmental was chosen by Nuffield Health to carry-out the detailed MEP and Process Design. Because the footprint of each site was different it was necessary to adapt the base design to suit each unit. During the process we worked very closely with two of the authors of Health Building Note 13 (HBN 13).

The Team
  • Client
    Nuffield Health
  • Architect
    Architect Design Group
  • Main Contractor
    CFES Limited
  • Services Contractor
    CFES Limited
  • Project Value:
    £25M
Systems Included
  • Reverse Osmosis Water Treatment
  • Clean Steam Generation
  • Standby Diesel Generator Set
  • UPS Systems
  • Integrated Control Systems
  • Steam Boilers with Dual Fuel System
  • Lamellar Flow Ventilation with HEPA Filters

project

NUFFIELD HEALTH PROJECT MANAGER

The government brought in new legislation with regard to the washing and sterilising of surgical instruments in the light of the CJD discovery. Nuffield Hospital could not comply with the new regulations within their current facilities.The Sterile Services Decontamination Project involved creating 6 strategically situated Decontamination Centre's each servicing the operating theatre instrument sterilisation requirements for a cluster of up to 9 hospitals. Each unit was created in an existing 1100 m2 industrial unit which was designed and "fitted-out" to healthcare and clinical laboratory standards to conform with the Department of Health’s new guidelines for Decontamination Centres (HBN 13).

Our Role

EDP Environmental was chosen by Nuffield Health to Project Manage this complex transition. EDP managed a team including Healthcare Planners, Architects, Logistics Consultants, Specialist Equipment Manufacturers and their Construction Partners.

Two of our team were part authors of Health Building Note 13 (HBN 13).

The Team
  • Client
    Nuffield Health
  • Architect
    Architect Design Group
  • Main Contractor
    CFES Limited
  • Services Contractor
    CFES Limited
  • Project Value
    £ 45M
Systems Included
  • Logistics – Sensitivity Potential Testing Sites
  • Site Acquisition - Identifying and Securing 6 Suitable Sites Operation & Staffing for New Operating Model
  • Construction – Designing, Building, Commissioning
  • Testing, Equipment – Sourcing of all Washer & Sterilisers

project

NUFFIELD HEALTH HOSPITAL REFURBISHMENT

Nuffield Health developed 6 Decontamination Centres to replace local sterile services facilities in the hospitals. This meant that the existing decontamination equipment needed to be removed from each of Nuffield Health’s 39 hospital sites. The areas were then refurbished for a range of new uses.

Our Role

EDP Project Managed the specialists companies and Nuffield Health staff at each of the 39 hospitals to the completion of each refurbishment.

The Team
  • Client
    Nuffield Health
  • Architect
    Cyril Sweett
  • Main Contractor
    Raidan
  • Services Contractor
    Raidan
  • Project Value
    £ 2.75M
Systems Included
  • Assess Accessibility for Removing Redundant Equipment.
  • Decommission, Remove and Dispose of Redundant Equipment.
  • Determine and Carry-Out Building Modifications Required.
  • Arrange for Washers and Sterilisers to be Scrapped.
  • Upgrade Washers and Sterilisers Depending on Size & Type.
  • Remodelling the Space Made Available.

project

St George’s Theatres

Refurbishment of 4 UCV Operating Theatres at St George’s Teaching Hospital in Tooting, South London. This was part of a rolling programme of works to refurbish many of their 43 Operating Theatres.

Our Role

EDP Environmental’s role combined the MEP Detailed Design Process, Project Management and Contract Administration. Activities included:-

⌲Feasibility Studies
⌲Preparation of the Client’s Scope of Works
⌲Developing the Client Brief and User Requirements
⌲Producing Detailed Technical Design for Tender
⌲Conducting the Tender Management Process
⌲Contract Administration and Site Management
⌲Project Management
The Team
  • Client
    St Georges Hospital
  • Architect
    CFES Ltd
  • Main Contractor
    CFES Ltd
  • Services Contractor
    CFES Ltd
  • Project Value
    £ 2.6M
Systems Included
  • Electrical Distribution
  • Lighting & Power
  • UPS Systems
  • Ventilation
  • Heating & Water Services
  • Medical Gases
  • Access Control & Communications

project

HERNE HILL FLATS

A new block of student accommodation apartments above a ground floor retail space for a Tesco Express.

Our Role

The full MEP Design of 8 different module types, the MEP Design of the common areas and landlord’s facilities and the MEP provisions for the retail shell. Part L Compliance and Energy Strategy.

The Team
  • Client
    Nordic Homes
  • Architect
    Hester Architects
  • Main Contractor
    Nordic Construction
  • Services Contractor
    Nordic Construction
  • Project Value
    £ 16M
Systems Included
  • Gas Fired Boilers
  • Hot Water Heated by CHP System
  • Electricity from CHP
  • Supplementary Heating from CHP
  • Central Plant Room
  • Large Hot Water Storage Facility
  • Fire Alarm System
  • Access Control System
  • CCTV
  • IT Infrastructure
  • Cable TV

project

ASCOT CORNER

The redevelopment of a brown field site with a block of 14 Apartments which were pre-built in modular form off-site.

The designs for the various modules differed slightly so it was important to distinguish between the generic and module specific elements.

Our Role

EDP Environmental provided the fully detailed MEP Design both for the modules and the site specific elements.  The EDP team visited the factory on a number of occasions to ensure that the MEP installations were carried out in accordance with UK standards.

The Team
  • Client
    Ascot Corner Development Company
  • Architect
    Hester Architects
  • Main Contractor
    Nordic Construction
  • Services Contractor
    Nordic Construction
  • Project Value
    £ 8M
Systems Included
  • Utility Supplies
  • Landlord’s Services
  • Electrical Distribution System
  • Small Power & Lighting
  • Heating and Hot & Cold Water Services
  • Ventilation
  • Fire Alarm System
  • Access Control System
  • Communications & Data Systems

project

WEST YARD FARM

The project consisted of the redevelopment of a number of existing farm buildings into a new house and the conversion of the barn, to provide an additional dwelling.

Our Role

EDP Environmental are delighted to have helped our Client in creating a truly environmentally conscious development. As well as providing the Mechanical and Electrical Design, EDP Environmental carried out the design of the sustainable systems.

The Team
  • Client
    Private Client
  • Architect
    Van Ellen & Sheryn
  • Main Contractor
    Goulden Brothers
  • Services Contractor
    PB Services
  • Project Value
    £ 1.6M
Systems Included
  • Ground Source Heat Pumps
  • Solar Thermal Hot Water
  • Solar PV
  • Log Burners

project

LONDON CRYO

A new treatment centre for sports and pain management for ‘LondonCryo’.

This is the first of a number of centres that will continue to be rolled out.

Our Role

To undertake the Mechanical and Electrical Services design and associated consultancy services

The Team
  • Client
    London Cryo
  • Architect
    Studio Octopi
  • Main Contractor
    Construction Management
  • Services Contractor
    Construction Management
  • Project Value
    £ 500K
Systems Included
  • Mechanical (Heat Recovery) Ventilation Systems
  • Heating System, Including Generation and Distribution
  • Domestic Hot and Cold Water Services
  • Lighting
  • Small Power
  • Fire Detection and Alarm
  • Security System
  • Above Ground (Foul) Drainage
  • Building Services Controls Systems
  • Incoming Services, Including Gas, Water and Electrical Supplies

project

Westlands Leisure Centre

The refurbishment of the existing sports hall and squash courts for South Somerset District Council, including new changing rooms, exercise studio and gym.

Our Role

EDP Environmental undertook the Mechanical and Electrical design.

The Team
  • Client
    Kirkham Board
  • Architect
    SSDC
  • Main Contractor
    EBC Ltd
  • Services Contractor
    Watertite
  • Project Value
    £ 900K
Systems Included
  • Heating
  • Ventilation
  • Lighting
  • Fire Alarm
  • Communications
  • Security
  • Smart Booking System
  • Lift