project

ROBERT CLACK LOWER SCHOOL

The project consists of the construction of a new Year 7 teaching block, incorporating 12 general classrooms and a food technology classroom.  The project also included the extensive refurbishment of the lower school kitchen and the creation of a new beauty teaching facility.

Our Role

EDP Environmental undertook the full Mechanical and Electrical Design Services.

The Team
  • Client
    Greenside Integrated Services
  • Architect
    Bond Bryan Architects
  • Main Contractor
    MID Group
  • Services Contractor
    Greenside Integrated Services
  • Project Value
    £ 3M
Systems Included
  • Mechanical (Heat Recovery) Ventilation Systems
  • Air Source Heat Pump Heating System, including Generation and Distribution
  • Domestic Hot and Cold Water Services
  • Lighting Design
  • Small Power Design
  • Fire Detection and Alarm
  • Security System
  • Above Ground (Foul) Drainage
  • Building Services Controls Systems
  • Incoming Services, including Gas, Water and Electrical Supplies
  • Photovoltaics