project

TOPSHAM COMMUNITY CENTRE

The existing library and community hall was  demolished and a new community centre built on the site.  The scheme includes a multi-purpose hall to accommodate dining and functions, kitchen, day centre, library, meeting rooms, fitness studio, treatment rooms and community offices.

Our Role

EDP Environmental initially provided an outline Mechanical and Electrical scheme design to satisfy the planning and funding conditions.  We then completed the detailed design of all Mechanical and Electrical services.

The Team
  • Client
    Estuary League of Friends
  • Architect
    Kirkham Board
  • Main Contractor
    Enelco Limited
  • Services Contractor
    Ourheat Limited
  • Project Value
    £ 1.5M
Systems Included
  • LED Low Energy Lighting
  • Underfloor Heating (UFH)
  • Natural Ventilation & Heat Recovery Units (NVHR)
  • CO2 Controls
  • Photo-voltaic Panels (PV)
  • BEMS – Building Energy Management System